Specialist
marine contractor Van Oord ACZ commenced construction on 1
March 2004 and the work is expected to be complete by September
2004. The majority of the work is currently taking place at
Hythe with the raising of the existing splash wall nearing
completion and the construction of the first of the large
rock structures is well underway.
The first
consignment of rock, which emanates from Larvik in Norway,
arrived on the beach on the evening of Monday 22 March. Deliveries
have been continuous day and night at high tide with construction
and placement of the groyne at low tide. It is hoped that
this 120m long x 28m wide structure will be completed before
the Easter Holiday.
Traffic and
pedestrian management is now in place at Sandgate and work
will shortly be starting on the construction of a new splash
wall.