Progress - 16 August 2004
This is
likely to be the penultimate report on the Scheme as works
begin to draw to a close.
All rock structures are now complete.
The construction of the concrete walkway on the large rock
structure continues with most of the slabs now complete and
the wave wall now under construction. Given good weather,
this should be complete within the next 2 weeks.
The final loads of beach were pumped
ashore over the weekend and the dredger has now returned to
Rotterdam. All that remains is to recover the material from
the low water mark and to reshape the beach to the required
profile.
Concrete placement to the rear of Castle
Road and Riviera Road continues with about half of the slabs
now complete. Up to 10 slabs are poured each day so progress
here is very fast and the maintenance gangway should be open
by the end of August.
The only other works remaining are
to repair the concrete sea wall nosing on Marine Walk, construct
and repair access steps onto the beach from Marine Walk and
finally to resurface Marine Walk which has been badly damaged
due to the heavy trafficking of plant and machinery. This
last operation is scheduled to take place during the second
week in September.
We are attempting to reuse as much
of the old groyne timber as possible and the contractor is
constructing a number of benches from the wood.
.
The scheduled opening date for the Scheme is 5 October.
Some photos of the works are attached.