Progress - 04 May 2004
The works
at Hythe are nearing completion. The majority of the promenade
is now open to the public and the improvements to the wave
wall should be complete by mid-May.
The rock revetment
at The Riviera is also nearing completion and the civils sub-contractor
is about to start on the construction of the maintenance gangway.
A photograph of the revetment under construction and prior
to backfilling is attached. The first rock structure is now
constructed with just a small amount of armour rock still
to be placed. Of the remaining three structures, work is progressing
on two and the third is about to commence. A photograph of
the large rock headland is attached showing the core rock
in place over the first stage.
On Sandgate
Esplanade, work continues at both ends and is slightly behind
programme. However, longer sections of promenade are now closed
to the public allowing work to progress at a faster rate.
A photograph of the highest section of wall at the eastern
end of the Esplanade is attached.