| Scheme
Progress - 1 June 2004
All sites
at Hythe are now finished apart from the installation of some
hand railings at a couple of locations.
At Sandgate Esplanade, work is progressing
well on the wave wall, which is now over 50% complete. Work
is under way on the raising of the maintenance gangway behind
Coast Guard Cottages and will commence this week at the eastern
end where the first operation will be to clear the shingle.
At The Riviera, the first few concrete slabs were successfully
poured last week (Photo) and the sub contractor proposes to
pour at least four slabs every other day where possible. There
are significant problems with access here, which means that
the concrete has to be pumped in from the western end of Marine
Walk.
The rock work is progressing well with
the barge deliveries set to be completed at the end of the
month. Placement continues on the last four rock structures
with no significant delays. (Photo) Planning for the concrete
walkway on the large rock headland is ongoing and the large
diameter concrete support rings are being prepared for placement
as soon as the core rock is in place.
The extension to the two sea outfalls
is due to start on 8 June and is expected to take about 4
weeks to complete.
We are now at the halfway point of
the Scheme.