Progress - 11 June 2004
At Sandgate
Esplanade, work is progressing well and is nearly complete
apart from a few accesses and some jointing. Work is well
under way on the raising of the maintenance gangway behind
Coast Guard Cottages and at the eastern end. The first of
the slabs should be poured next week. At The Riviera, the
contractor is pouring up to 14 slabs each week so progress
is up to schedule.
The rock work is still on target with
the last rock delivery expected in about 3 weeks time. All
of the 4 structures are taking shape and can be seen at low
tide from the vantage point on the Leas.
The extension to the two sea outfalls
started as planned this week and the piles are in place ready
to receive the pipes.
The 'Volvox Iberia', the dredger for
the beach nourishment is due to arrive on 21 June and this
operation is expected to take 10 weeks. A total of 350,000m³
will be deposited on the beach. This equates to around 3 trips/day
with a load of 3,000m³/trip.