Progress - 30 July 2004
The delivery
pipe has now been moved to its third and final location at
Marine Walk, Folkestone and shingle will continue to be pumped
ashore for the next 2 weeks. The last infill section between
the eastern structures will be filled by dumper.
Rock placement is now complete on the
large rock structure and the construction of the concrete
walkway has commenced on top of the concrete supports. The
final barge arrived earlier this week and work will continue
on the two remaining rock structures for the next two weeks.
Concrete placement on The Riviera is
now finished, the remaining rocks have been replaced and work
has started on the slabs at the back of Castle Road in Sandgate.
The new rising main has been installed for Southern Water
and this is currently undergoing a test. The remainder of
the maintenance gangway is now open to the public.
Some photos of the works are attached.